Clean Coal Technology

1999, (01)

[Print This Page] [Close]
Current Issue | Archive | Advanced Search

AN ANALYSIS AND EVALUATION OF THE GAS CLEAN UP PROCESS EQUIPMENT AND TECHNICAL EQUIPMENT CHARACTERISTICS IN FOUR IGCC DEMONSTRATION POWER PLANTS

Xu Shisen Wei Shirang (Thermal Power Research Institute; State Electric Power Corporation;

Abstract:

The gas clean up process equipments and technical characteristics in Wabash River (262 MW, USA), Tampa (250 MW, USA), Demkolec (253 MW, Holland) and Purtollano (300 MW, Spain) IGCC demonstration power plants were analyzed and evatuated in this paper. The operation experiences and existed problems of the four power plants were also discussed. It is important for the gas clean-up process selection in first Chinese IGCC power plant

Key Words: combine cycle, synthetic gas, clean up process

Abstract:

Keywords:

Foundation:

Author: Xu Shisen Wei Shirang (Thermal Power Research Institute; State Electric Power Corporation;