分析评价大型IGCC电站中煤气净化工艺的设备和技术特点AN ANALYSIS AND EVALUATION OF THE GAS CLEAN UP PROCESS EQUIPMENT AND TECHNICAL EQUIPMENT CHARACTERISTICS IN FOUR IGCC DEMONSTRATION POWER PLANTS
许世森,危师让
Xu Shisen Wei Shirang (Thermal Power Research Institute; State Electric Power Corporation;
摘要(Abstract):
详细叙述了美国WabashRiver和Tampa、荷兰Demkolec、西班牙Puertolano4座250~300MW等级的大型IGCC示范电站煤气净化工艺的设备和技术特点,并进行了综合分析评价,明确了煤气净化工艺在4座示范电站中存在的问题。这对中国第一座IGCC示范电站选择煤气净化工艺路线具有一定的参考价值。
The gas clean up process equipments and technical characteristics in Wabash River (262 MW, USA), Tampa (250 MW, USA), Demkolec (253 MW, Holland) and Purtollano (300 MW, Spain) IGCC demonstration power plants were analyzed and evatuated in this paper. The operation experiences and existed problems of the four power plants were also discussed. It is important for the gas clean-up process selection in first Chinese IGCC power plant
关键词(KeyWords):
联合循环电站,净化工艺,分析
combine cycle, synthetic gas, clean up process
基金项目(Foundation):
作者(Authors):
许世森,危师让
Xu Shisen Wei Shirang (Thermal Power Research Institute; State Electric Power Corporation;